Olkaria III Geothermal Power Project
ClientOrmat Power
EngineerORPOWER4 INC. USA
Completion date2000
Project ValueUS$ 2.85 Million









Construction of a 3 x 4 MW Geothermal Power Station for a private power producer ORMAT Power. H Young undertook the building and civil works including:

Earthworks - 50,000m3
Concrete works - 11,000m3


Mechanical installation of 3 x 4 generating turbines, transformers, cooling towers.

H Young also undertook the installation of more than 6 Kms of high pressure steam and other piping works including the insulation and cladding.

The project took only five and a half months from a green site to power production.

 
 
© 2008 H Young & Co, (EA) Ltd  