| Client | Ormat Power |
|---|
| Engineer | ORPOWER4 INC. USA |
|---|
| Completion date | 2000 |
|---|
| Project Value | US$ 2.85 Million |
|---|
|
Construction of a 3 x 4 MW Geothermal Power Station for a private power producer ORMAT Power. H Young undertook the building and civil works including:
Earthworks - 50,000m3
Concrete works - 11,000m3
Mechanical installation of 3 x 4 generating turbines, transformers, cooling towers.
H Young also undertook the installation of more than 6 Kms of high pressure steam and other piping works including the insulation and cladding.
The project took only five and a half months from a green site to power production.
|